Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Actual Site Pics as on Dec 2017
Side View of Building 1 and 2
July 2017
Building 1 with podium
July 2017
Building 2 - Work completed
July 2017
Building 1 - Back View (Garden view)
July 2017
95 % work completed.
June 2017
Podium work completed.
June 2017
95 % work completed.
June 2017
95 % work completed.
June 2017
95 % work completed.
June 2017
95 % work completed.
June 2017
95% work completed.
May 2017
95% work completed.
May 2017
95% work completed.
May 2017
95% work completed.
May 2017
Painting completed. Removal of Bamboos
May 2017
95% work completed.
May 2017
95% work completed.
May 2017
95% work completed.
May 2017
95% work completed.
May 2017
95% work completed.
May 2017
95% work completed.
May 2017
95% work completed.
May 2017
95% work completed.
May 2017
Building no. 1
April 2017
Building no. 2
April 2017
Bld.1 Painting work near completion.
April 2017
Bld.1 Painting work near completion.
April 2017
Building no. 2 Work completed
April 2017
Building no. 2 Work completed
April 2017
Bld.1: Painting work completed.
March 2017
Bld.1: Back elevation.
March 2017
Podium work in progress.
March 2017
Podium work in progress.
March 2017
Building.2 - Painting work completed.
February 2017
Building.1 - Painting work in progress (Front side)
February 2017
Building.1 - Painting work in progress (Back side)
February 2017
Podium work in progress
February 2017
Building.1 - Painting work Started
January 2017
Building.2 - Painting work near completion
January 2017
Building.2 - Painting work near completion
January 2017
Podium work in progress
January 2017
Building 1 - Back side External Plaster complete
December 2016
Building 1 - Front side External Plaster complete
December 2016
Building 2 - Painting in Progress
December 2016
Building 1 - Front Elevation
November 2016
Building 2 - Front Elevation
November 2016
Building 2 - Plaster done
November 2016
External plaster completed
November 2016
Final Slab Building 1 - Back Elevation
November 2016
Plaster completed till 23rd floor
November 2016
Plaster in progress
November 2016
Side elevation
November 2016